Closed
Milestone Feb 25, 2023–Feb 26, 2023

Create a data route from IB net to the ScienceDMZ

Establish a network path for data flows through the Science DMZ to allow for high throughput data transfers.

This includes:

  • creating a NAT configuration to route traffic from IB through the external segment DTN (dtn1-sd)
  • install nagios port monitoring on dtn_1 to observe throughput
  • select a set of compute nodes to use dtn_1 as their default route
  • remove them from their existing partitions for dedicated use a transfer nodes
  • create a sciencedmz partition for the compute nodes with this default route
  • assign authorized jobs to the sciencedmz partition
  • Work items 3
  • Merge requests 0
  • Participants 2
  • Labels 1
Loading
Loading
Loading
Loading
100% complete
100%
Start date
Feb 25, 2023
Feb 25
-
Feb 26 2023
Due date
Feb 26, 2023 (Past due)
3
Work items 3
Open: 0 Closed: 3
0
Merge requests 0
Open: 0 Closed: 0 Merged: 0
0
Releases
None
Reference: rc%"Create a data route from IB net to the ScienceDMZ"